Client:
Air Separation Plant - Delaware Valley
Problem:
Client
experienced fire damage on industrial wood cooling tower
which was critical to its operation. Owner needed to determine
full extent of the damage, and obtain a cost proposal
and time frame for making the necessary repairs. Reducing
downtime was a major consideration for all contractors
who chose to bid on this work. Ability to sufficiently
man the project in a timely fashion was to be a determining
factor in awarding the work. |
Solution:
Calvitti
Co. made an immediate and thorough inspection of the unit
to assess the damage. Recommendations for repairs were
proposed along with the costs associated with them, and
a projection for completion of the work – all within
24 hours of the inspection. Using materials from stock
and timely deliveries from certified cooling tower vendor
sources, our company was not only able to complete the
work ahead of schedule, but also do so within budget to
the total satisfaction of the customer. |
Ask
Us About this Case Study |